Tasks for TeraPaths
(all figures following tasks show: (start month, length of task in months)
Planning and design of TeraPaths new functionality (0, 1) - 9/2009
- Make decision on layer 2 or layer 3 reservations based on source and target sites; decide on uni-directional or bi-directional reservations (1, 2) - 10/2009 - 11/2009
- Find reservation that minimizes reservedEndTime: design, implement, test, and evaluate distributed reservation negotiation (2, 12) - 11/2009 - 10/2010
- Search related literature, design algorithm, and plan implementation (2, 3) - 11/2009 - 1/2010
- Design and implement database to maintain additional information to facilitate negotiation across sites (3, 2) - 12/2009 - 1/2010
- Implement end-site reservation negotiation based on new parameters, come up with list of possible reservations, considering desiredMaxBandwidth (4, 8) - 1/2010 - 8/2010
- Negotiate with current OSCARS implementation - trial and error using selected reservations (6, 6) - 3/2010 - 8/2010
- Run tests and evaluate algorithm and implementation (11, 3) - 8/2010 - 10/2010
- Implement web service based API and necessary code to accommodate the new interaction between SRM and TeraPaths (11, 4) - 8/2010 - 11/2010
- Design and development of “local-null” (consultant) mode (12, 6) - 9/2010 - 2/2011
- Setup TeraPaths testbed between BNL-Michigan and integrate into the end storage systems (SRM/BeStMan) (16, 2) - 1/2011 - 2/2011
- Functional, reliability, and performance tests under stand-alone mode and integrated mode (18, 4) - 3/2011 - 6/2011
- Plan testbed between BNL-LBNL (12, 12) - 9/2010 - 8/2011
- Deploy TP and BeStMan (18, 2) - 3/2011 - 4/2011
- System test and add ESCPScope for monitoring (15, 3) - 12/2010 - 2/2011
- Test multi-user data transfer requests (20, 4) - 5/2011 - 8/2011
- Final project report (21, 3) - 6/2011 - 8/2011